信息系统项目管理师2005年上半年

● ___(66)___ is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.

This method includes following types of dependencies or precedence relationships:

___(67)___the initiation of the successor activity, depends upon the completion of the predecessor activity.

___(68)___the initiation of the successor activity, depends upon the initiation of the predecessor activity.

(66) A.PDM B.CPM C.PERT D.AOA

(67) A.F-S B.F-F C.S-F D.S-S

(68) A.F-S B.F-F C.S-F D.S-S

● estimating schedule activity costs involves developing an ___(69)___ of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of ___(70)___ to facilitate comparisons both within and across projects. the ___(71)___ describes important information about project requirement that is considered during cost estimating.

(69) A.accuracy B.approximation C.specification D.summary

(70) A.activity B.work C.currency D.time

(71) A.project scope statement B.statement of work

C.project management plan D.project policy

● The ___(72)___ technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

(72) A.cost aggregation B.reserve analysis

C.parametric estimating D.funding limit reconciliation

● ___(73)___ is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype

(73) A.milestone B.deliverable C.etc D.BAC

● ___(74)___ are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

(74) A.controls B.baselines

C.project stakeholders D.project managers

第1页

你可能喜欢

  • 工程项目信息管理
  • 项目管理信息系统实施
  • 投资项目管理师真题
  • 工程项目管理设计
  • 2008网络管理员下半年下
  • 项目制管理
  • 建设项目

热门文档

相关文档

站点地图 | 文档上传 | 侵权投诉 | 手机版
新浪认证  诚信网站  绿色网站  可信网站   非经营性网站备案
本站所有资源均来自互联网,本站只负责收集和整理,均不承担任何法律责任,如有侵权等其它行为请联系我们.
文档下载 Copyright 2013 doc.docsou.com All Rights Reserved.  闽ICP备15022310号-9  闽公网安备 35021102001881号  email
返回顶部